Category: Chase St. Bridge Replacement
The City of Sonoma is pleased to announce that the Chase Street Bridge over Nathanson Creek, connecting Broadway and Austin Ave, is now officially open to both vehicle and foot traffic! After months of hard work and dedication, we are excited to provide a safer and more efficient crossing for our community. We would like … Continued
We are delighted to announce a significant milestone achieved this week in the Chase Street Bridge Replacement Project. The construction team, led by Granite Construction Company, and the construction management team from Ghirardelli Associates Inc., have successfully completed the pouring of the bridge deck. Next Steps: With the bridge deck now in place, our focus … Continued
We are pleased to provide you with the latest update on the Chase Street Bridge Replacement Project, highlighting recent progress and a modification to the working schedule. Concrete Foundation Pour: We are excited to report significant progress in the construction of the Chase Street Bridge Replacement Project. Over the past week, our contractor, Granite Construction, … Continued
We wanted to inform the community about upcoming construction activity related to the Chase Street Bridge Replacement Project. Our contractors have been making good progress and will continue to work on Saturday, August 12th, between 9:00 AM to 6:00 PM. This additional workday has been scheduled to ensure that we meet our milestones efficiently. We … Continued
The Chase Street Bridge is now closed to through traffic due to construction related to the Chase Street Bridge Replacement Project. The closure began on July 5, 2023, and is expected to last approximately 6 months. We apologize for any inconvenience this may cause and appreciate your understanding during this essential infrastructure improvement. This project … Continued
The City of Sonoma invites the public to attend a groundbreaking ceremony for the Chase Street Bridge Replacement Project. The ceremony will take place on Monday, June 19, 2023, at 10:00 a.m., on the west side of the Chase Street Bridge located on Chase Street over Nathanson Creek, between Broadway and Austin Ave in Sonoma. The groundbreaking … Continued
On May 17th, 2023, the City Council awarded the contract for construction of the bridge to Granite Construction. The contract includes bridge replacement and relocation of water and sewer services, demolishing and replacement of existing concrete curb, gutter and sidewalk and/or residential driveway. The City received additional funding from the Federal Bridge and Highway Program … Continued
On April 19th, 2023, the City Council granted the contract for the construction management of the Chase St Bridge to Ghirardelli Associates Inc. This construction management encompasses a range of services, including resident engineering and construction inspection, public outreach and assistance, materials and source inspection and testing, stormwater pollution prevention quality assurance, construction staking quality … Continued
The City of Sonoma is requesting proposals for Construction Management, Inspection, and Materials Testing Services. The City is seeking to retain a Construction Management and Material Testing consultant firm(s) with licensed professional civil, geotechnical engineers, and material testers for the Chase Street Bridge Replacement Project Federal Project BRLS-5114 (016). Proposals are due: Thursday, August 18, … Continued